For over two years, segments of the felled Francis Scott Key Bridge have stood in the Patapsco River, serving as an eerie reminder of the span’s demise.

Next year, finally, they’re slated to be demolished.

Maryland officials agreed Thursday morning to a $38.6 million contract with the Pittsburgh-based Joseph B. Fay Co. to raze the remnants. Preliminary work will start next month, with more significant demolition beginning in January and February, according to the Maryland Transportation Authority.

Rather than using explosives, the work is expected to be done mechanically. A large excavator positioned on a barge will use an extended arm to hammer into the residual roadway, turning it into rubble, which will then be scooped up and recycled.

Advertise with us

“There will be a barge there to catch the concrete. Anything they don’t catch, they’ll use a clamshell [dredge] to get it out of the water and put it on the barge,” MDTA chief engineer Jim Harkness said in an interview.

“You’ll just see them start poking away at this thing.”

Maryland had originally pegged Kiewit, a construction giant, for the entire rebuild project — including demolition — but earlier this year the two parties could not agree on the timeline and cost.

Instead, the state broke the project into four separate contracts, the first being the demolition approved Thursday.

The most expensive contract, by far, will be for construction of the overwater span of the bridge. The authority is currently reviewing a short list of builders for that mega-contract, worth billions, and will consider more specific proposals in a few months. It is expected to select one by the summer.

Advertise with us

The authority has maintained for a year that its expected completion date is the end of 2030, although that goal came before it switched from Kiewit. In a formal request in July concerning the overwater portion, the authority asked that builders complete the work as close to Dec. 31, 2030, “as practicable.”

Much of the old bridge was destroyed or has been demolished, but some observers point to the remnants still jutting out of the Patapsco River as evidence of a lack of progress.

However, demolition is entirely uncoupled from construction of the new bridge. Because the new span will be slightly southeast of the old one, the foundation has been built even as portions of the old bridge remain.

“That demolition, it doesn’t affect us. They’re not in the way of any of our other three contracts,” Harkness said.

Part of the reason the state did not proceed with Kiewit was that the contractor expected the rebuild to cost about $9 billion, significantly more than the state’s roughly $5 billion cost estimate. That figure had grown from an initial estimate of $2 billion.

Advertise with us

When the state divided the rebuild into segments, it sought to increase competition and keep costs down. At least for the demolition, that effort seems to have worked. The state had projected the contract would go for between $50 million and $100 million.

In addition to demolition, Joseph B. Fay Co. will complete other work to prepare the new bridge’s foundation. For example, piles that are 200 feet long and 8 feet in diameter have been hammered into the riverbed, but they now have sludge in them, which will need to be cleaned out.

“If you think of it as a giant straw,” Harkness said, “and you put that straw into a milkshake, you’re going to have that milkshake inside the straw, too, right?”

Crews will soon use a massive drill to break up soil within the piles, then suck the muck out.

Last month, the authority launched an online progress dashboard — basically a Domino’s Pizza order tracker for the bridge. It shows the completion percentages for various parts of the rebuild: for example, construction of wooden platforms to assist with rebuilding efforts is 100% finished.